Sunday, September 23, 2007

Finished 1st Floor Columns


In Septeber 2007, first floor composite columns were erected; pest control system and some water pipes were installed to both houses.

1-story house, roof beam was constructed.

Wednesday, September 12, 2007

Piling, Foundation Peir, and Ground Beam

For 2.5 months, piling was driven, foundation piers and ground beams were completed for both houses.




Sunday, September 9, 2007

Inspiration and Perspective

We inspired the housing style from houses at Palm Hill Golf Club, Hua Hin. To develop our own, we like modern contemporary style, after long fine-tuning with architect, we finally get perspectives. The project comprises of 2 houses, 1-story and 2-story, with swimming pool in front of the house. They look relaxed, cozy and comfortable.


Land at Lakewood

We bought a piece of land at Lakewood Village, Bangna-Trad Km 18. The land is approx. 432 sq.w. located on the main road and the other side is along the golf course, No. 3 hole - Wood Course. This is where our project was started...

Land. From road, you can see fair way and lots of trees.